The project
- Challenge
- A 21 t chamber measuring 8 × 3 × 2.5 m had to be lifted through a dedicated opening into a technical room of a healthcare building.
- What we did
- Unloading, internal transport, crane lift through the technological opening and precise final positioning, plus handling of all peripheral equipment.
- Result
- Chamber and equipment installed exactly to requirements, so commissioning started without delay.
21 tchamber
8 mlong
1week
Scope of work
- Unloading of the chamber and peripheral equipment
- Transport of components to the technical room
- Lift through a dedicated technological opening
- Precise positioning at the final location
Equipment on site: 100–150 t mobile crane · 3.5 t forklift · 3 t mobile gantry · rigging and installation tools



More projects
Similar work
USAOEM
EV batteries · OEM installation
Battery production line installation in Indiana
Samsung · new battery plant, Indiana, USARead the case study →Europe
Packaging & label materials · Relocation
Industrial slitter line moved from Germany to Denmark
Avery Dennison · Gotha (DE) → Hedehusene (DK)Read the case study →N. AmericaEurope
Automotive · International relocation
Production equipment moved from Mexico to Poland
Maflow · Mexico → Toruń, PolandRead the case study →Relocation calculator
Budget range in 60 seconds
Tell us what moves and where. You get an indicative range and a call-back from the right regional team. Every enquiry lands in CRM with its region.