EURELO Industrial Group (EIG) › Projects › Mixer system replaced in a running plant
Building materials · OEM installation

Mixer system replaced in a running plant

Sofraden (OEM) for ARDEX Scandinavia · Denmark

Case study

The project

Challenge
An interconnected mixer system with pneumatics, hoppers, conveyors and steel platforms had to come out safely inside an active plant, with minimum downtime.
What we did
Dismantling of the mixer, pneumatics, pipes, valves, hoppers, screw conveyor, steel beams, stairs and the first-floor platform, then installation of the new equipment to specification under EURELO supervision.
Result
New mixing equipment integrated precisely into the existing process.
4weeks
1live plant
1mixer system replaced
ClientSofraden (OEM) for ARDEX Scandinavia
LocationDenmark
Timeline4 weeks
DatesJuly – August 2026

Scope of work

  • Dismantling of the mixer system and supporting structure
  • Removal of pneumatic components, pipes and valves
  • Dismantling of hand-add stations and raw material hoppers
  • Removal of structural beams, stairs and first-floor platform
  • Installation of new equipment to client specification
  • On-site supervision by EURELO specialists
Mixer system replaced in a running plantMixer system replaced in a running plantMixer system replaced in a running plant
Relocation calculator

Budget range in 60 seconds

Tell us what moves and where. You get an indicative range and a call-back from the right regional team. Every enquiry lands in CRM with its region.

Start a project

Tell us what moves. We'll plan the rest.

Get a quote →
EURELO project deskQuick answers · a project manager replies within one working day