EURELO Industrial Group (EIG) › Projects › Eight battery production lines installed in Hungary
EV batteries · OEM installation
Eight battery production lines installed in Hungary
Samsung · automotive battery plant, Hungary
Case study
The project
- Challenge
- Eight complete anode and cathode lines for automotive batteries, each arriving in around 300 × 40 ft containers, had to be installed over several years of plant expansion.
- What we did
- Offloading, unpacking and handling, internal transport and positioning, crane and forklift coordination and mechanical assembly under OEM supervision, with 20 operatives and 2 project managers.
- Result
- Eight full production lines delivered, proving large-scale installation, logistics and OEM coordination.
8lines installed
~300containers per line
20operatives · 2 PMs
Scope of work
- Offloading, unpacking and handling of ~300 × 40 ft containers per line
- Internal transport and equipment positioning
- Mechanical assembly under OEM supervision
- Crane and forklift coordination
- Support during commissioning

More projects
Similar work
USAOEM
EV batteries · OEM installation
Battery production line installation in Indiana
Samsung · new battery plant, Indiana, USARead the case study →Europe
Packaging & label materials · Relocation
Industrial slitter line moved from Germany to Denmark
Avery Dennison · Gotha (DE) → Hedehusene (DK)Read the case study →N. AmericaEurope
Automotive · International relocation
Production equipment moved from Mexico to Poland
Maflow · Mexico → Toruń, PolandRead the case study →Relocation calculator
Budget range in 60 seconds
Tell us what moves and where. You get an indicative range and a call-back from the right regional team. Every enquiry lands in CRM with its region.