EURELO Industrial Group (EIG) › Projects › Snacks packing line rebuilt in three weeks
FMCG · Dismantling & installation

Snacks packing line rebuilt in three weeks

Kellanova · Project Monty roll-out, K5 European Snacks

Case study

The project

Challenge
An existing snacks packing line had to be dismantled and rebuilt with new and modified machinery in a short window.
What we did
Dismantling and removal of Gasser, Seamer and Disc Feeder machines and conveyors, electrical cabinet replacement, then assembly, positioning and anchoring of the new machinery.
Result
One integrated mechanical and electrical team took the line from dismantling to final installation smoothly.
3weeks
1integrated team
2disciplines
ClientKellanova
LocationKellanova plant, Europe
Timeline3 weeks
DatesApril – May 2026

Scope of work

  • Dismantling of Gasser, Seamer and Disc Feeder machines
  • Removal of secondary packing conveyors and safety barriers
  • Electrical cabinet disconnection and replacement on the mezzanine
  • Assembly and positioning of new machinery
  • Installation of modified Quality Street components
  • Final anchoring of machines and conveyors
Snacks packing line rebuilt in three weeksSnacks packing line rebuilt in three weeks
Relocation calculator

Budget range in 60 seconds

Tell us what moves and where. You get an indicative range and a call-back from the right regional team. Every enquiry lands in CRM with its region.

Start a project

Tell us what moves. We'll plan the rest.

Get a quote →
EURELO project deskQuick answers · a project manager replies within one working day